Primary Current Injection Trip Test is specified for low-voltage power circuit breakers in maintenance testing at clause 7.6.1.2.B.5 of ANSI/NETA MTS-2023.

Value: low-voltage power circuit breakers

ProvenanceANSI/NETA MTS-2023 supports data record tests.primary-current-injection-trip-test.equipment.breaker.maintenance, which is cited on the entry Primary Current Injection Trip Test.SOURCEANSI/NETA MTS-2023ANSI/NETA MTS-2023Licensed standard, clause 7.6.1.2.B.5DATA RECORDtests.primary-current-injection-trip-test.equipment.breaker.maintenancetests.primary-current-in..Verified 2026-10-13ENTRYPrimary Current Injection Trip TestPrimary Current Injectio..No revisions
Provenance. Where this record comes from and where it is used: the cited source, the record itself and the entry that cites it.
Provenance: the chain from source to entry.
StepItemDetail
SourceANSI/NETA MTS-2023Licensed standard, clause 7.6.1.2.B.5
Data recordtests.primary-current-injection-trip-test.equipment.breaker.maintenanceVerified 2026-10-13
EntryPrimary Current Injection Trip TestNo revisions
Subject
Primary Current Injection Trip Test (Test methods)
Kind
Equipment fact
Source
ANSI/NETA MTS-2023, clause 7.6.1.2.B.5, Maintenance Testing Specifications for Electrical Power Equipment and Systems, NETA. Publisher page

History

Every recorded change to this data record, oldest first.
DateChange
2026-10-13created

Cite this page

Cite the governing standard for the fact itself; cite this page as the finding aid.

"Data record tests.primary-current-injection-trip-test.equipment.breaker.maintenance." Circuit Breaker Reference. 2026-10-13. https://www.circuitbreakerreference.com/data/tests.primary-current-injection-trip-test.equipment.breaker.maintenance/.